Every scheme starts with a constraint: the water, the ground, the budget or the season. These are projects we have worked on, and what changed once the water was running.

System assessments
Pumpstation Suction Design: Farm Dam Siphon

Two farm pumpstations could not draw enough water from their dams. A siphon design delivered full suction capacity at both, with no new pumps and no drained dams.

Read the case study →
Civil & site infrastructure
Howick Fuel Retail Centre: Civil & Stormwater Design

Ant Consult delivered the civil design for a Shell-branded fuel retail centre in Howick — earthworks, stormwater attenuation, potable and fire water, sanitation and fuel tank civils on a steep, saturated site.

Read the case study →
Masterplans
Mount Verde Estate Hydraulic Masterplan

Ant Consult carried out a detailed hydraulic masterplan study for the Mount Verde Estate to inform phased future development.

Read the case study →
Commercial irrigation design
Mouton Citrus: 135 ha Drip Irrigation Design

Complete drip irrigation design for a 135 ha citrus development, engineered for phased expansion, energy efficiency and long-term operational flexibility.

Read the case study →
Masterplans
NADEC Hail: 190 ha Agro-Industrial Hub Masterplan

A 190 ha crop and processing hub outside Hail, masterplanned as one site: two parallel water networks, a route for RO reject that exceeds 4,000 m³ a day, and phased costs.

Read the case study →
System assessments
Water Loss Investigation: Aloe Ridge Estate

A hydraulic investigation of Aloe Ridge Villages 1 and 2 that separated real leakage from normal consumption, and gave Capital City Housing a costed fix.